Milestone Achieved at Rotterdam


On the 19th of March 2025, the last section of the climbing core wall was poured, reaching its final height of +152.90 m.

It has been a long and challenging journey, started in November 2023 – 43x castings with a sensational average speed rate of 7.3 days per floor – made possible only by proactive and professional cooperation between all parties involved!


Our group

General contracting

Specialized contracting

Other activities