- Dittaino, Italy
- Mass Transit
- Ongoing (Completion date: 2026)
€588M
Total investmentHighlights
- 20 viaducts on the new line (tot. 7.1 km);
- 3 viaducts on the historic line (tot. 82 m);
- 3 natural tunnels (tot. 2.7 km);
- 2 artificial tunnels (tot. 0.4 km)
Description
The project, being carried out on behalf of RFI Rete Ferroviaria Italiana and partially financed by the PNRR revitalization plan, is the executive design and construction of 23 km of the new Palermo-Catania railway, with many works of art including viaducts and tunnels as well as the construction of the new Catenanuova railway station.