Crown Princess Mary Bridge – Frederikssund Fjord Link
New Orbital Highway and Truck Route
Massive infrastructure project that transform road travel in Qatar and allows to be traversed from north to south
- Doha, Qatar
- Bridges & Viaducts
- Completed: 2017
$50M
Total investmentHighlights
- 2,168 segments (depth 2,1 m);
- Total length of elevated structures 6,185 m;
- Average span of viaducts 36 m, max. 42 m;
- Deck area 83,650 sqm.
Description
Design and Construction of Precast Concrete Bridges on the New Orbital Highway & Truck Route (P023), located South-West from Doha.
Rizzani de Eccher was involved in constructing 45 km of road network and designing and building the elevated structures for four major interchanges (Junctions 15-18).
Scope of work included production and erection of 2,168 precast concrete segments (single-cell box girders), including provision of labor, materials and equipment. The viaducts were erected via balance cantilever method.